Site Equipment Limited stock a specialist, comprehensive range of Grundoburst Pipebursting Equipment.
We currently have available 400G and 800G Rigs
400G Rig Ready for Delivery
The 400G rig will burst pipes up to and including 150mm
The 800G rig will burst pipes up to and including 400mm (ground conditions permitting)
The standard tooling you get with the rig will burst all materials of Pipe – excluding Ductile Steel
In the event a Ductile Steel Pipe is being Burst, we can provide as an extra accessory, a rollerblade !

Grundoburst 400G Pulling New Pipe To Rig – c/w Ductile Steel Roller Blade Attached
The Grundoburst Rig uses a QuickLock Rod System
The quicklock rod system is very easy, to use.
With a full kit you will get 144no quicklock rods, which are 0.8mtrs long and will Burst 100mtrs.

It is absolutely imperative all operators of the bursting rigs are trained and competent.
400G and 800G Tooling Accessories
Tooling Set Up Required for Cast Iron, Asbestos Cement & UPVC Material Pipes
1no 100mm Delta Wing Blade, 1no Quicklock Elbow, 1no Expander Connection, 1no Guiding Cone, 1no Expander 165, 1no Pipe Puller 125
Tooling Set Up Required for Ductile and Steel Material Pipes
1no 100mm Roller Blade, 1no Quicklock Elbow, 1no Expander Connection, 1no Guiding Cone, 1no Expander 165, 1no Pipe Puller 125
Size of Pit for 400G Bursting Rigs
We recommend the pit for the rig is a minimum 3.0mtrs Long and at least 1.0mtr wide. The bottom of the pit must be kept as dry as possible.
The Bursting rig must be fixed to the base of the pit – any movement will affect the bursting operation.
WARNING NEVER STAND BEHIND THE RIG IN THE PIT
When Bursting Pipes, you must always burst the back of the collar first.
When you are feeding the Pilot Rod through the existing pipe, and when you are bursting, we always recommend the use of an operative, monitoring the operations (walking) along the line of the pipe, that is being burst.
We also recommend all parties on site have use of 2 way radios.
It is absolutely imperative a complete detailed planning survey is carried out along the bursting line, checking for all existing services, and hidden objects that may be present.
NO PIPEBURSTING IS TO BE STARTED WITHOUT ALL PLANNING AND SERVICE CHECKS CARRIED OUT THOROUGHLY
All site equipment quick lock rods comply with TTUK testing and inspection procedure.
PB30 Pipebursting Equipment

We also have available PB30 Pipebursting rigs that will burst pipes upto and including 100mm.
PB30 Pipebursting Rig PB30 Head Unit in Pit
For a PB30 specification data sheet click here